Understand procurement governance

Approval models

Single approver, chains per cost centre, parallel cost centres.

Most customers' approval policies come in a handful of shapes, and almost every written policy is one of them or a combination. Recognising which one you are being asked for saves a configuration project, and tells you early whether the approval rules can express it.

The vocabulary first

An approval rule is built from four pieces, and they stay separate all the way down into the configuration:

  • A condition: what has to be true for the rule to match. A fixed amount, the cost centre's remaining budget, the buyer's personal limit, a role the buyer holds, a permission the buyer lacks, or always.
  • An effect: what happens when it does. Hold the cart for approval, refuse it outright, or record that somebody should be told.
  • A scope: whether the rule applies to one cost centre or to the whole cart.
  • An approver and a sequence: who signs, and in which position of that cost centre's chain.

Almost every argument about approval workflows is really an argument about one of those four, and separating them ends most of them.

Model 1: single step by value

The commonest policy in the Mittelstand and the right default. One threshold, one approver.

Anything over €1,000 goes to the Werkstattleiter.

One rule: condition Constant limit with a limit of 1,000, effect Pending order (needs approval), approver the Werkstattleiter. A cart of exactly €1,000 does not match; €1,000.01 does. Under the limit, the order is placed.

Fits: companies up to roughly 100 people, or a single site with one obvious authority. Most customers should start here even if their written policy is richer, because a policy nobody has operated yet is a guess.

Watch for: the threshold set too low. €250 in a workshop that orders consumables daily produces ten approvals a day, and the control dies of exhaustion within a quarter. Set it where it catches the orders somebody would actually want to see.

Model 2: chains in sequence

Two or more signatures, one after the other.

Order valueSignatures needed
up to €1,000none
€1,000 – €10,000Werkstattleiter
over €10,000Werkstattleiter, then Geschäftsführung

There is no separate "chain" object. The chain is what you get when several rules on the same cost centre match one cart. Each matching rule with the effect Pending order creates one approval, and the approvals of one cost centre are worked through by the rule's sequence number: only the lowest open one can be decided, and approving it opens the next.

The table above is two rules on the same cost centre:

RuleConditionSequenceApprover
Werkstatt ab 1.000Constant limit 1,0000Werkstattleiter
Werkstatt ab 10.000Constant limit 10,0001Geschäftsführung

A €5,000 cart matches only the first rule and needs one signature. A €12,000 cart matches both and needs two, in sequence order. The value bands come from the conditions; the order of signatures comes from the sequence, never from the amounts. Give each rule on a cost centre its own sequence number, so the order is never left to chance.

Rules with no cost centre form one chain of their own and are measured against the whole cart.

Fits: 100–1,000 people, or any company with an insurer or a bank imposing a dual-signature threshold. A Vier-Augen-Prinzip clause above a fixed amount is common in German practice and is exactly this model.

Watch for: one decline ends the whole request, at any step. The Geschäftsführung saying no after the Werkstattleiter said yes leaves nothing to order, and the buyer starts again from a cart.

Model 3: parallel cost centres

Parallel approval exists in one form: across cost centres. A cart with lines on 4711 (Werkstatt) and KST-2200 (Instandhaltung) carries two chains, one per cost centre, and neither waits for the other. Each cost-centre owner decides their own share. The request becomes an order only when every approval on every chain is given, and a single decline on either side ends it.

That is the right shape when the two approvers answer different questions about different money. The Werkstatt owner is asked about the Werkstatt's budget; the Instandhaltung owner about theirs. Sequencing them would add a day and improve nothing.

Two approvers on the same cost centre always form a chain. If a customer asks for "the cost-centre owner and the controller, at the same time", the nearest you can offer is the two in sequence, or the controller informed rather than asked (below).

Watch for: asking for an approval where a notification is meant. If the controller never declines anything, they do not want an approval. A rule with the effect Send email records that they should be told and never holds the cart. The procurement app sends no mail itself: the notification is written to the request's history and published as an event, so delivering it is a matter for the system that picks it up.

Holidays: plan for them in the rules

The approval rules have no deputies, no escalation and no expiry. A request waits for the approver it names until somebody decides it. That makes the choice of approver type the holiday plan:

Approver typeWho may decideSurvives a holiday?
ContactExactly that contactNo. The request waits for them
RoleAny contact holding the named roleYes, if more than one person holds it
Default (accountable contact)The cost centre's accountable contact, looked up when the cart is submittedOnly if you change the accountable contact before the request is submitted

And there is the override: an administrator can clear every open approval on a request at once (Super-approve) or cancel a waiting request. In the Cockpit both sit on the purchase request. See The approver's path.

A named contact is a single point of failure. If the only approver for the Werkstatt is one person by name, the Werkstatt stops ordering above the limit every August. Use a role where two people can sign, and agree with the customer who uses the override when neither is there.

Which model fits which customer

CustomerModelWhy
Under 50 people, one siteSingle step by value, one global ruleMore structure than this will not be maintained
50–300, several departmentsSingle step per cost centre, approver Default (the accountable contact)Authority follows the budget, which is how they already think
300–1,000, formal controllingChains of two or three rules per cost centre, approvers by roleThere is an insurer or an auditor behind the second signature
Over 1,000, own procurement systemNone of the aboveTheir workflow lives in SAP Ariba, Coupa or Onventis. Use punchout and leave approval to their system

That last row is the one people skip. For a large buyer, reproducing their approval matrix in your shop is a project with no end: their policy changes twice a year and yours would have to follow. Punchout hands the cart back to their system, and every approval happens on their side.

How this works in the Revenue Cloud

Rules are rows, not code. You maintain them under Procurement › Approval rules. Each rule carries a name, an optional cost centre, a sequence, a condition with its parameters, an effect with its parameters, an approver, a Show condition switch and an Active switch.

Conditions:

ConditionMatches whenAsked of
AlwaysEvery cart the rule applies toprocurement
Constant limitThe amount is above a fixed limitprocurement
Contact has roleThe buyer holds one of the named rolesprocurement
Contact missing permissionThe buyer lacks one of the named permissionsprocurement
Available budgetThe cost centre's share is more than its remaining budget. Only on a rule with a cost centrecost-centers
Personal limitThe amount is more than the buyer's personal limit. Whole cart, or one cost centre's sharecost-centers

A rule with a cost centre measures only that centre's share of the cart and does nothing when the cart books nothing to it. A rule without one measures the whole cart.

Effects:

EffectResult
Pending order (needs approval)The cart becomes a purchase request with one approval for this rule
PreventThe cart is refused with the rule's reason. No request, no order
Send emailA notification is recorded, naming who should hear about it. Whether the cart needs approval is unchanged

When several rules match, Prevent wins over everything, then Pending order; Send email never changes the outcome. A notification is recorded only for a cart that becomes a purchase request.

Prevent is the hard stop and Pending order the soft one. "Hard limit" and "soft limit" mean exactly that everywhere in this area: a property of the rule's effect, not of the budget.

Show condition lets the shop tell the buyer which kind of condition caught the cart, for example Personal limit. The parameters, such as the amount, are never passed on.

Next